(東北大學(xué) 資源與土木工程學(xué)院,沈陽(yáng) 110006;
2. 馬鞍山礦山研究院, 馬鞍山 243004)
摘 要: 對(duì)房柱式空?qǐng)霾傻V法采場(chǎng)頂板破壞模式及其影響因素進(jìn)行了探討,建立了識(shí)別頂板破壞模式的知識(shí)庫(kù),并用VC++語(yǔ)言開(kāi)發(fā)出了識(shí)別頂板破壞模式的專(zhuān)家系統(tǒng)。實(shí)際應(yīng)用表明,用該專(zhuān)家系統(tǒng)識(shí)別的頂板破壞模式與實(shí)際的頂板破壞模式基本吻合。
關(guān)鍵字: 空?qǐng)霾傻V法;頂板破壞模式; 專(zhuān)家系統(tǒng)
hanging wall of room-and-pillar mining
(1. College of Resource and Civil Engineering, Northeastern University,
Shenyang 110006, P.R.China;
2. Ma′anshan Institute of Mining Research, Ma′anshan 243004, P.R.China)
Abstract:The failure mode of hanging wall of roomand pillar mining was investigated. A knowledge base in identifying the failure mode of hanging wall was built. An expert system was developed with VC++computer language to identify possible failure modes of hanging wall at given geological and mining conditions. The application of expert system in actual mines shows that the identified failure modes of hanging wall by this expert system have good agreement with the actual.
Key words: room-and-pillar mining; failure mode of hanging wall; expert system